Government |
Project
|
Development
Programs Used
|
Current
Status |
| Amity |
Wastewater
Improvements |
$3
million in loans and grants
approved |
Construction
is approximately 95% complete |
| Aumsville |
Wastewater
Improvements |
W/W $2,237,469 |
Application
submitted |
| Aumsville |
Water
Improvements |
W/W
$486,000 |
Application
work started |
| Carlton |
Current
Land Use Planning |
Local
funds |
Land
use planning services continued
throughout the year on an "as
needed" basis |
| Carlton |
Downtown
streetscape imporvements
|
CDBG
$300,000
Local $80,000 |
Construction
contract out to bid in February |
| Detroit |
Current
Land Use Planning |
Local
funds |
Land
use planning services continued
throughout the year on an "as
needed" basis |
| Detroit |
Water
System Improvements |
Local
funds |
Work
began on funding applications
for water system improvements |
| Canyon
Regional Sewer Project (Detroit
& Idanha) |
Regional
Sewer Project |
|
The
project is currently being re-evaluated
by funding agencies and the cities |
| Falls
City |
Current
Land Use Planning |
Local
funds |
Land
use planning services continued
throughout the year on an "as
needed" basis |
| Falls
City |
New
community center and fire hall |
CDBG
$600,000 Private foundation support
also being sought |
Project
being re-bid due to high construction
costs and very high previous bids |
| Gates |
Water
System Improvements |
CDBG
and W/W $1,200,000 |
Initial
project intake completed. Application
work started. |
| Gervais |
Housing
Rehabilitation |
CDBG
$300,000 |
100%
of the initial grant funds loaned
out to eligible homeowners. |
| Gervais |
Downtown
Streetscape |
CDBG
$3,000,000
W/W $45,000 |
Application
submitted. |
| Gervais |
Current
Land Use Planning |
Local
funds |
Land
use planning services continued
throughout the year on an "as
needed" basis. |
| Hubbard |
Current
Land Use Planning |
Local
funds |
Land
use planning services continued
throughout the year on an "as
needed" basis. |
| Hubbard |
Community
Center |
CDBG
$20,000 |
Feasibility
study completed in June 2004.
Awaiting community decision. |
| Idanha |
Current
Land Use Planning |
Local
funds |
Land
use planning services continued
throughout the year on an "as
needed" basis. |
| Independence |
Current
Land Use Planning |
Local
funds |
Land
use planning services continued
throughout the year on an "as
needed" basis. |
| Jefferson |
Housing
rehabilitation |
CDGB
re-lending |
As
original loans are repaid, additional
houses have been rehabilitated. |
| Lafayette |
Water
System Improvements |
SDWRLF
$114,000
Local funds $300,000 |
Construction
completed on improvements intended
to remove lead and copper. |
| Marion
County |
Housing
rehabilitation |
CDBG
$300,000 |
Project
75% completed |
| Marion
County |
Sheltered
workshop training building for
Rockwest, Inc. |
CDBG
$600,000 |
Design
completed. Construction scheduled
for early Spring, 2005. |
| McMinnville |
Farmworker
Primary Care Clinic |
CDBG
$600,000
Private $1,250,000 |
Construction
completed. |
| Mt.
Angel |
Current
Land Use Planning |
Local
funds |
Land
use planning services continued
throughout the year on an "as
needed" basis. |
| Mt.
Angel |
Charles
Street redesign |
RIF
$35,000 |
Completed. |
| Mt.
Angel |
Housing
rehabilitation |
Local
funds |
Program
assistance was provided on an
"as needed" basis throughout
the year. |
| Salem |
Downtown
conference center development
and related downtoan planning |
EDA
technical assistance funds |
A
grant for EDA funds was approved
and the project started in May,
2003 and was completed in July,
2004. |
| Scotts
Mills |
Water
System Design and construction |
CDBG
$718,000
Rural Dev. $1.2 million |
Preliminary
funding application work and environmental
review completed. Design underway
in early Spring, 2005. |
| Scotts
Mills |
Current
Land Use Planning |
Local
funds |
Land
use planning services continued
throughout the year on an "as
needed" basis. |
| Sheridan |
Sewer
Facility Plan |
CDBG
$100,000 |
Facility
Plan completed |
| Silverton |
Housing
rehabilitation |
Local
funds |
Program
assistance was provided on an
"as needed" basis throughout
the year. |
| Sublimity |
Current
Land Use Planning |
Local
funds |
Land
use planning services continued
throughout the year on an "as
needed" basis. |
| Stayton |
Housing
Rehabilitation |
CDBG
grant $250,000 |
100%
of the grant funds loaned out
to eligible homeowners. Closed
out in July, 2004. |
| Willamina |
Sewer
System Improvements |
CDBG
$750,000;
W/W $1,837,946;
Local $150,000 |
Construction
95% complete |
| Willamina |
New
water line to connect Willamina
and Sheridan and serve the county's
largest private emplyers |
CDBG
$40,000 |
Application
work underway. |
| Yamhill
County |
Public
Transportation Study |
RIF
$44,000 |
COG
continued to provide staff to
a countywide public transportation
study. It was completed in July,
2004. |
| |
Yamhill
Parkway Committee |
Local
funds/Regional Investment Fund |
Staff
continued to provide support to
the group steering the development
of the Newberg/Dundee By-Pass. |